Project: High speed railway. Section Ourense-Amoeiro
Start end dates: April 2006-May 2008
Client: Isolux-Corsán SA
Description: Total length 756 m, 16 spans of 50 m. Maximum pier hegth 70 m. Executed with overhead movable scaffolding system (mms).